Railway Engineering The reception signal isi) outer signalii) home signaliii) starteriv) advanced starter The correct answer is (ii) and (iii) (iii) and (iv) (i)and(iv) (i) and (ii) (ii) and (iii) (iii) and (iv) (i)and(iv) (i) and (ii) ANSWER DOWNLOAD EXAMIANS APP
Railway Engineering In a scissors cross-over, the crossings provided arei) 2 obtuse angle crossingsii) 4 obtuse angle crossingsiii) 4 acute angle crossingsiv) 6 acute angle crossingsThe correct answer is (ii) and (iv) (i)and(iv) (ii) and (iii) (i) and (iii) (ii) and (iv) (i)and(iv) (ii) and (iii) (i) and (iii) ANSWER DOWNLOAD EXAMIANS APP
Railway Engineering The formation width for a single line meter gauge track in embankment as adopted on Indian Railways is 4.27 mm 4.55 mm 4.88 mm 5.49 mm 4.27 mm 4.55 mm 4.88 mm 5.49 mm ANSWER DOWNLOAD EXAMIANS APP
Railway Engineering The cross-sectional area of 52 kg flat footed rail is 7235 mm² 6615 mm² 7825 mm² 6155 mm² 7235 mm² 6615 mm² 7825 mm² 6155 mm² ANSWER DOWNLOAD EXAMIANS APP
Railway Engineering A Broad Gauge branch line takes off as a contrary flexure from a main line If the superelevation required for branch line is 10 mm and cant deficiency is 75 mm, the superelevation to be actually provided on the branch line will be 10 mm 85 mm 65 mm 15 mm 10 mm 85 mm 65 mm 15 mm ANSWER DOWNLOAD EXAMIANS APP
Railway Engineering The height of the center of arm of a semaphore signal above the ground is 6.5 m 8.5m 5.5m 7.5 m 6.5 m 8.5m 5.5m 7.5 m ANSWER DOWNLOAD EXAMIANS APP