Industrial Engineering and Production Management The most popular type of organisation used for Civil Engineering Constructions is Line and staff organization Line organization Functional organization Effective organization Line and staff organization Line organization Functional organization Effective organization ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management The standard time for a job is Total work content + delay contingency allowance Total work content + basic time Total work content Base time + relaxation time Total work content + delay contingency allowance Total work content + basic time Total work content Base time + relaxation time ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management For handling materials during manufacture of cement, a _________ is widely used. Belt conveyor Fork lift truck Overhead crane Bucket conveyor Belt conveyor Fork lift truck Overhead crane Bucket conveyor ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management Which of the following organizations is best suited for steel plants Functional organization Line, staff and functional organizations Line organization Staff organization Functional organization Line, staff and functional organizations Line organization Staff organization ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management Which of the following is independent of sales forecast? Production control Production planning Productivity Inventory control Production control Production planning Productivity Inventory control ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management When slack of an activity is positive Any one of the above It represents a situation where extra resources are available and the completion of project is not delayed The activity is critical and any delay in its performance will delay the completion of whole project It represents that a programme falls behind schedule and additional resources are required to complete the project in time Any one of the above It represents a situation where extra resources are available and the completion of project is not delayed The activity is critical and any delay in its performance will delay the completion of whole project It represents that a programme falls behind schedule and additional resources are required to complete the project in time ANSWER DOWNLOAD EXAMIANS APP