Industrial Engineering and Production Management If E is the duration, ES and EF are die earliest start and finish times, LS and LF are latest start and finish times, then the following relation holds good LF = LS + D All of these LS = LFD EF = ES + D LF = LS + D All of these LS = LFD EF = ES + D ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management The time taken by a trained worker to perform an operation, while working a steady pace, is known as Normal time Representative time Standard time None of the listed here Normal time Representative time Standard time None of the listed here ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management The main objective of work measurement is to Plan and schedule of production Estimate the selling prices and delivery dates Formulate a proper incentive scheme All of these Plan and schedule of production Estimate the selling prices and delivery dates Formulate a proper incentive scheme All of these ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management The two bin system is concerned with Forecasting sales Production planning Despatching and expediting Ordering procedure Forecasting sales Production planning Despatching and expediting Ordering procedure ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management The time of completing a project in network analysis is given by following time of the critical activity meeting at the final triode Early start Early finish Late start Late finish Early start Early finish Late start Late finish ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management Simplex method is the method used for Network analysis Linear programming Queuing theory Value analysis Network analysis Linear programming Queuing theory Value analysis ANSWER DOWNLOAD EXAMIANS APP