Industrial Engineering and Production Management In process layout Production control is more difficult and costly All of these Routing and scheduling is more difficult Handling and backtracking of materials is too much Production control is more difficult and costly All of these Routing and scheduling is more difficult Handling and backtracking of materials is too much ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management Pick up the correct statement. Dummy activity on a PERT/CPM chart means, it Consumes time, but no resources Is a dangling event Consumes resources but no time Consumes neither time nor resources Consumes time, but no resources Is a dangling event Consumes resources but no time Consumes neither time nor resources ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management A low unit cost can be obtained by following Specialization of operation Automatic material handling equipment Product layout Functional layout Specialization of operation Automatic material handling equipment Product layout Functional layout ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management Statistical quality control techniques are based on the theory of Probability Statistics All of the these Quality Probability Statistics All of the these Quality ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management Acceptance sampling is widely used in Batch production All of these Mass production Job production Batch production All of these Mass production Job production ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management When slack of an activity is negative All of these The activity is critical and any delay in its performance will delay the completion of whole project It represents that a programme falls behind schedule and additional resources are required to complete the project in time It represents a situation where extra resources are available and the completion of project is not delayed All of these The activity is critical and any delay in its performance will delay the completion of whole project It represents that a programme falls behind schedule and additional resources are required to complete the project in time It represents a situation where extra resources are available and the completion of project is not delayed ANSWER DOWNLOAD EXAMIANS APP