Estimating and Costing The inspection pit or chamber is a manhole provided in a base drainage system At every change of direction At every 30 m intervals All of these At every change of gradient At every change of direction At every 30 m intervals All of these At every change of gradient ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The concrete work for the following part of the building of specified thickness is measured in square meters Floors Root slabs Wall panels All of these Floors Root slabs Wall panels All of these ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The expected out turn of half brick partition wall per mason per day is 4.0 m2 5.0 m2 1.5 m2 2.0 m2 4.0 m2 5.0 m2 1.5 m2 2.0 m2 ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The expected out turn for earth work in excavation in ordinary soil per workman per day is 2.00 cum 4.00 cum 3.00 cum 1.00 cum 2.00 cum 4.00 cum 3.00 cum 1.00 cum ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The 'centre line method' is specially adopted for estimating Octagonal buildings Hexagonal buildings Circular buildings All of these Octagonal buildings Hexagonal buildings Circular buildings All of these ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The measurement is not made in square meters in case of R.C. Chhajja P.C. (Damp proof course) Concrete Jeffries Form works R.C. Chhajja P.C. (Damp proof course) Concrete Jeffries Form works ANSWER DOWNLOAD EXAMIANS APP