Estimating and Costing The expected out turn for earth work in excavation in ordinary soil per workman per day is 2.00 cum 4.00 cum 1.00 cum 3.00 cum 2.00 cum 4.00 cum 1.00 cum 3.00 cum ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing While estimating the qualities for the construction of a building, the correct metric unit is Meter for length Liter for capacity Cubic metre for area Square meters for volume Meter for length Liter for capacity Cubic metre for area Square meters for volume ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The area of a sloping surface of a protective embankment of mean height‘d’, side slopes S: 1 and length ‘L’ is √[d² × (ds)²] 2 L.D √(1 + s²) L.D √(1 + s²) d × d × s √[d² × (ds)²] 2 L.D √(1 + s²) L.D √(1 + s²) d × d × s ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing For 100 sq. m cement concrete (1 : 2: 4) 4 cm thick floor, the quantity of cement required, is 1.00 m³ 0.98 m³ 0.94 m³ 0.90 m³ 1.00 m³ 0.98 m³ 0.94 m³ 0.90 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The reduced levels of points, 30 metres apart along the longitudinal section of a road portion between chainages 5 and 9 are shown in the given figure. If there is a uniform up-gradient of the road 120 in 1, the chainage of the point with no filling or cutting is (6 + 18) chains (6 + 12) chains (6 + 15) chains None of these (6 + 18) chains (6 + 12) chains (6 + 15) chains None of these ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The diameter of a domestic sewer pipe laid at gradient 1 in 100 is recommended 100 mm 200 mm 150 mm 175 mm 100 mm 200 mm 150 mm 175 mm ANSWER DOWNLOAD EXAMIANS APP