Estimating and Costing The expected out turn for earth work in excavation in ordinary soil per workman per day is 3.00 cum 4.00 cum 1.00 cum 2.00 cum 3.00 cum 4.00 cum 1.00 cum 2.00 cum ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Due to change in price level, a revised estimate is prepared if the sanctioned estimate exceeds 0.05 0.04 0.025 0.02 0.05 0.04 0.025 0.02 ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The brick work is not measured in cu m in case of One or more than one brick wall Brick work in arches Half brick wall Reinforced brick work One or more than one brick wall Brick work in arches Half brick wall Reinforced brick work ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing While preparing a detailed estimate Area should be measured correct to 0.01 sqm Dimension should be measured correct to 0.01 m All of these Volume should be measured correct to 0.01 cum Area should be measured correct to 0.01 sqm Dimension should be measured correct to 0.01 m All of these Volume should be measured correct to 0.01 cum ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The minimum width of a septic tank is taken 70 cm 80 cm 90 cm 75 cm 70 cm 80 cm 90 cm 75 cm ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The assumption on which the trapezoidal formula for volumes is based, is The mid-area of a pyramid is half the average area of the ends The end sections are parallel planes The volume of the Prismoidal is over-estimated and hence a Prismoidal correction is applied All listed here The mid-area of a pyramid is half the average area of the ends The end sections are parallel planes The volume of the Prismoidal is over-estimated and hence a Prismoidal correction is applied All listed here ANSWER DOWNLOAD EXAMIANS APP