Estimating and Costing The expected out turn for earth work in excavation in ordinary soil per workman per day is 2.00 cum 4.00 cum 3.00 cum 1.00 cum 2.00 cum 4.00 cum 3.00 cum 1.00 cum ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The unit of measurement is per quintal for the following: Expanded metal wire netting Rolling shutters Collapsible gates with rails M.S. reinforcement of R.C.C. works Expanded metal wire netting Rolling shutters Collapsible gates with rails M.S. reinforcement of R.C.C. works ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing In long and short wall method of estimation, the length of long wall is the centre to centre distance between the walls and Breadth of the wall Half breadth of wall on each side None of these One fourth breadth of wall on each side Breadth of the wall Half breadth of wall on each side None of these One fourth breadth of wall on each side ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The expected out turn of cement concrete 1 : 2 : 4 per mason per day is 3.5 m³ 5.0 m³ 1.5 m³ 2.5 m³ 3.5 m³ 5.0 m³ 1.5 m³ 2.5 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Pick up the item whose weight is added to the weight of respective item, is Bolts All listed here Brackets Cleats Bolts All listed here Brackets Cleats ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The detention period in a septic tank is assumed 25 minutes 30 minutes 40 minutes 20 minutes 25 minutes 30 minutes 40 minutes 20 minutes ANSWER DOWNLOAD EXAMIANS APP