Estimating and Costing The expected out turn for earth work in excavation in ordinary soil per workman per day is 4.00 cum 3.00 cum 2.00 cum 1.00 cum 4.00 cum 3.00 cum 2.00 cum 1.00 cum ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The trap which is provided to disconnect the house drain from the street sewer is called Master trap Intercepting trap All listed here Interception manhole Master trap Intercepting trap All listed here Interception manhole ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The excavation exceeding 1.5 m in width and 10 sq.m in plan area with a depth not exceeding 30 cm, is termed as Surface excavation Surface dressing Excavation Cutting Surface excavation Surface dressing Excavation Cutting ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Referring of given figure, pick up the correct statement from the following: Length of short walls in-to-in is 3.20 m Length of long wall out-to-out is 6.80 m All listed here The total length of centre line of four walls is 20 m Length of short walls in-to-in is 3.20 m Length of long wall out-to-out is 6.80 m All listed here The total length of centre line of four walls is 20 m ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The expected out turn of half brick partition wall per mason per day is 2.0 m2 4.0 m2 5.0 m2 1.5 m2 2.0 m2 4.0 m2 5.0 m2 1.5 m2 ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The rate of payment is made for 100 cu m (per % cu m) in case of Excavation in trenches for foundation All of these Rock cutting Earth work in excavation Excavation in trenches for foundation All of these Rock cutting Earth work in excavation ANSWER DOWNLOAD EXAMIANS APP