Estimating and Costing The expected out turn for earth work in excavation in ordinary soil per workman per day is 4.00 cum 3.00 cum 1.00 cum 2.00 cum 4.00 cum 3.00 cum 1.00 cum 2.00 cum ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing For 100 sq. m cement concrete (1 : 2: 4) 4 cm thick floor, the quantity of cement required, is 0.94 m³ 0.90 m³ 0.98 m³ 1.00 m³ 0.94 m³ 0.90 m³ 0.98 m³ 1.00 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The height of the sink of wash basin above floor level is kept 70 cm 75 cm to 80 cm 80 cm 60 cm 70 cm 75 cm to 80 cm 80 cm 60 cm ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The slope of the outlet of 'P trap' below the horizontal is kept 12° 8° 10° 14° 12° 8° 10° 14° ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The cross-section of a road partly in banking and partly in cutting is shown in the given figure. The area of the shaded portion is ⅓ × (b - rd)²/(r + s) ⅓ × (b - rd)²/(s - r) ½ × (b + rd)²/(r - s) ⅓ × (b - rd)²/(r - s) ⅓ × (b - rd)²/(r + s) ⅓ × (b - rd)²/(s - r) ½ × (b + rd)²/(r - s) ⅓ × (b - rd)²/(r - s) ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The trap which is provided to disconnect the house drain from the street sewer is called Interception manhole Intercepting trap All listed here Master trap Interception manhole Intercepting trap All listed here Master trap ANSWER DOWNLOAD EXAMIANS APP