Estimating and Costing The expected out turn for earth work in excavation in ordinary soil per workman per day is 2.00 cum 4.00 cum 3.00 cum 1.00 cum 2.00 cum 4.00 cum 3.00 cum 1.00 cum ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The rate of an item of work depends on Proportion of mortar All of these Specifications of materials Specifications of works Proportion of mortar All of these Specifications of materials Specifications of works ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The main factor to be considered while preparing a detailed estimate, is Availability of materials Quantity of the materials All of these Transportation of materials Availability of materials Quantity of the materials All of these Transportation of materials ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The reduced levels of points, 30 metres apart along the longitudinal section of a road portion between chainages 5 and 9 are shown in the given figure. If there is a uniform up-gradient of the road 120 in 1, the chainage of the point with no filling or cutting is (6 + 12) chains (6 + 18) chains None of these (6 + 15) chains (6 + 12) chains (6 + 18) chains None of these (6 + 15) chains ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The floor area includes the area of the balcony up to 1 0.5 0.25 0.75 1 0.5 0.25 0.75 ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing While preparing a detailed estimate Area should be measured correct to 0.01 sqm Dimension should be measured correct to 0.01 m All of these Volume should be measured correct to 0.01 cum Area should be measured correct to 0.01 sqm Dimension should be measured correct to 0.01 m All of these Volume should be measured correct to 0.01 cum ANSWER DOWNLOAD EXAMIANS APP