Construction Planning and Management The grade resistance factor for an earth moving machine can be obtained by multiplying grade percentage by a factor approximately equal to 6 kg/tonne 9 kg/tonne 20 kg/tonne 2 kg/tonne 6 kg/tonne 9 kg/tonne 20 kg/tonne 2 kg/tonne ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Time and progress chart of a construction, is also known as All listed here Modified Mile stone chart Gantt chart Bar chart All listed here Modified Mile stone chart Gantt chart Bar chart ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the expected time for completion of a project is 10 days with a standard deviation of 2 days, the expected time of completion of the project with 99.9% probability is 6 days 10 days 4 days 16 days 6 days 10 days 4 days 16 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the output of a drag-line for 90° angle of swing at optimum depth of cut is X, then the output for 120° angle of swing at 120 % of optimum depth of cut will be Less than X Any of the above Equal to X More than X Less than X Any of the above Equal to X More than X ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which one of the following represents an event? Fixing of door Concrete cured Selecting sites Plastering of walls Fixing of door Concrete cured Selecting sites Plastering of walls ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management While scheduling a project by C.P.M. All listed here A project is divided into various activities Required time for each activity is established Net work is drawn by connecting the activities and the events All listed here A project is divided into various activities Required time for each activity is established Net work is drawn by connecting the activities and the events ANSWER DOWNLOAD EXAMIANS APP