Construction Planning and Management
If the optimistic time, most likely time and pessimistic time for activity A are 4, 6 and 8 respectively and for activity B are 5, 5.5 and 9 respectively, then

expected time of activity B is greater than the expected time of activity A
expected time of both activities A and B are same
None of these
expected time of activity A is greater than the expected time of activity B

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Latest start of an activity is always

equal to latest event time of preceding node
greater than or equal to latest event time of preceding node
less than or equal to latest event time of preceding node
less than latest event time of preceding node

ANSWER DOWNLOAD EXAMIANS APP