Construction Planning and Management The grade resistance factor for an earth moving machine can be obtained by multiplying grade percentage by a factor approximately equal to 9 kg/tonne 20 kg/tonne 6 kg/tonne 2 kg/tonne 9 kg/tonne 20 kg/tonne 6 kg/tonne 2 kg/tonne ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Power stations are generally treated as Electrical construction Light construction Heavy construction Industrial construction Electrical construction Light construction Heavy construction Industrial construction ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The area under the Beta distribution curve is divided into two equal parts by Optimistic time Expected time Pessimistic time Most likely time Optimistic time Expected time Pessimistic time Most likely time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which of the following is a weakness of bar chart? All of these Interdependencies of activities Uncertainties Project progress All of these Interdependencies of activities Uncertainties Project progress ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The normal time required for the completion of project in the above problem is 19 days 13 days 9 days 14 days 19 days 13 days 9 days 14 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A four wheel truck or whose operating weight is 12000 kg is pulled along a road having a rising slope of 2% at a uniform speed. Assume grade resistance factor = 10 kg/tonne. The tension in the tow cable is 720 kg. The rolling resistance of the road will be 40 kg/tonne 20 kg/tonne 50 kg/tonne 30 kg/tonne 40 kg/tonne 20 kg/tonne 50 kg/tonne 30 kg/tonne ANSWER DOWNLOAD EXAMIANS APP