Highway Engineering The ductility value of bitumen for suitability in road construction should not be less than 20 cm 10 cm 30 cm 50cm 20 cm 10 cm 30 cm 50cm ANSWER DOWNLOAD EXAMIANS APP
Highway Engineering Bitumen of grade 80/100 means its penetration value is 10 mm its penetration value is 8 to 10 mm its penetration value is 8 mm its penetration value is 8 to 10 cm its penetration value is 10 mm its penetration value is 8 to 10 mm its penetration value is 8 mm its penetration value is 8 to 10 cm ANSWER DOWNLOAD EXAMIANS APP
Highway Engineering When a number of roads are meeting at a point and only one of the roads is important, then the suitable shape of rotary is elliptical circular tangent turbine elliptical circular tangent turbine ANSWER DOWNLOAD EXAMIANS APP
Highway Engineering When two equally important roads cross roughly at right angles, the suitable shape of central island is tangent circular elliptical turbine tangent circular elliptical turbine ANSWER DOWNLOAD EXAMIANS APP
Highway Engineering The most suitable equipment for compacting clayey soils is a vibrator sheep foot roller pneumatic tyred roller smooth wheeled roller vibrator sheep foot roller pneumatic tyred roller smooth wheeled roller ANSWER DOWNLOAD EXAMIANS APP
Highway Engineering Tie bars in cement concrete pavements are at warping joints expansion joints contraction joints longitudinal joints warping joints expansion joints contraction joints longitudinal joints ANSWER DOWNLOAD EXAMIANS APP