Highway Engineering In the penetration macadam construction, the bitumen is Sprayed after the aggregates are spread and compacted Sprayed before the aggregates are spread and compacted Premixed with aggregates and then spread None of these Sprayed after the aggregates are spread and compacted Sprayed before the aggregates are spread and compacted Premixed with aggregates and then spread None of these ANSWER DOWNLOAD EXAMIANS APP
Highway Engineering The maximum width of a vehicle as recommended by IRC is 1.85 m 4.72 m 2.44 m 3.81 m 1.85 m 4.72 m 2.44 m 3.81 m ANSWER DOWNLOAD EXAMIANS APP
Highway Engineering RC-2, MC-2 and SC-2 correspond to viscosity in increasing order from RC-2 to SC-2 same viscosity None of these viscosity in decreasing order from RC-2 to SC-2 viscosity in increasing order from RC-2 to SC-2 same viscosity None of these viscosity in decreasing order from RC-2 to SC-2 ANSWER DOWNLOAD EXAMIANS APP
Highway Engineering Which of the following shapes is preferred in a valley curve ? lemniscate spiral cubic parabola simple parabola lemniscate spiral cubic parabola simple parabola ANSWER DOWNLOAD EXAMIANS APP
Highway Engineering The camber of road should be approximately equal to half the longitudinal gradient two times the longitudinal gradient longitudinal gradient three times the longitudinal gradient half the longitudinal gradient two times the longitudinal gradient longitudinal gradient three times the longitudinal gradient ANSWER DOWNLOAD EXAMIANS APP
Highway Engineering Stopping sight distance is always equal to overtaking sight distance more than overtaking sight distance less than overtaking sight distance None of these equal to overtaking sight distance more than overtaking sight distance less than overtaking sight distance None of these ANSWER DOWNLOAD EXAMIANS APP