Highway Engineering
In the penetration macadam construction, the bitumen is

Sprayed before the aggregates are spread and compacted
Premixed with aggregates and then spread
Sprayed after the aggregates are spread and compacted
None of these

ANSWER DOWNLOAD EXAMIANS APP

Highway Engineering
Select the correct statement.

All of these
Minimum and maximum values of group index can be 0 and 20 respectively
More the value of CBR, greater thickness of pavement will be required
More the value of group index, less thickness of pavement will be required

ANSWER DOWNLOAD EXAMIANS APP

Highway Engineering
With increase in speed of the traffic stream, the maximum capacity of the lane

first increases and then decreases after reaching a maximum value at optimum speed
first decreases and then increases after reaching a minimum value at optimum speed
decreases
increases

ANSWER DOWNLOAD EXAMIANS APP