Building Construction Sum of tread and rise must lie between 400 to 450 mm 300 to 350 mm 500 to 550 mm 600 to 650 mm 400 to 450 mm 300 to 350 mm 500 to 550 mm 600 to 650 mm ANSWER DOWNLOAD EXAMIANS APP
Building Construction Pick up the correct specification of one-room quarters generally adopted from the following: Six quarters in a row The size of room is either 3.5 m × 3 m or 4.2 m × 2.5 m The front verandah is kept 2 m wide All listed here Six quarters in a row The size of room is either 3.5 m × 3 m or 4.2 m × 2.5 m The front verandah is kept 2 m wide All listed here ANSWER DOWNLOAD EXAMIANS APP
Building Construction Pile foundation is generally provided if soil is Compressible Made up Water logged All listed here Compressible Made up Water logged All listed here ANSWER DOWNLOAD EXAMIANS APP
Building Construction The form work from the underside of slabs, can be removed only after 7 days 1 day 4 days 14 days 7 days 1 day 4 days 14 days ANSWER DOWNLOAD EXAMIANS APP
Building Construction The triangular portion between any two adjacent arches and the tangent to their crowns, is Spandril Rise Haunch Soffit Spandril Rise Haunch Soffit ANSWER DOWNLOAD EXAMIANS APP
Building Construction To support a heavy structure in sandy soil, the type of foundation generally used, is Combined footing Pier footing Raft footing Strap footing Combined footing Pier footing Raft footing Strap footing ANSWER DOWNLOAD EXAMIANS APP