Railway Engineering On a single rail track, goods trains loaded with heavy iron material run starting from ‘A’ to ‘B’ and then empty wagons run from ‘B’ to ‘A’. The amount of creep in the rails: Will be maximum at the middle of A and B Will be more in the direction of B to A Cannot be determined from the given data Will be more in the direction of A to B Will be maximum at the middle of A and B Will be more in the direction of B to A Cannot be determined from the given data Will be more in the direction of A to B ANSWER DOWNLOAD EXAMIANS APP
Railway Engineering Consider the following surveys.1. Reconnaissance survey2. Preliminary survey3. Traffic survey4. Location surveyThe correct sequence in which these surveys are conducted before the alignment of a track is finalised is 3,1,2,4 1,3,2,4 1,3,4,2 3,1,4,2 3,1,2,4 1,3,2,4 1,3,4,2 3,1,4,2 ANSWER DOWNLOAD EXAMIANS APP
Railway Engineering Which of the following turnouts is most commonly used for goods train on Indian Railways ? 1 in 12 1 in 8’/2 1 in 20 1 in 16 1 in 12 1 in 8’/2 1 in 20 1 in 16 ANSWER DOWNLOAD EXAMIANS APP
Railway Engineering Number of dog spikes normally used per rail seat on curved track is one on either side two outside and two inside one outside and two inside two outside and one inside one on either side two outside and two inside one outside and two inside two outside and one inside ANSWER DOWNLOAD EXAMIANS APP
Railway Engineering In a scissors cross-over, the crossings provided arei) 2 obtuse angle crossingsii) 4 obtuse angle crossingsiii) 4 acute angle crossingsiv) 6 acute angle crossingsThe correct answer is (i) and (iii) (ii) and (iv) (i)and(iv) (ii) and (iii) (i) and (iii) (ii) and (iv) (i)and(iv) (ii) and (iii) ANSWER DOWNLOAD EXAMIANS APP
Railway Engineering Which of the following devices is used to transfer the wagons or locomotives to and from parallel tracks without any necessity of shunting ? traverser triangle scotch block turntable traverser triangle scotch block turntable ANSWER DOWNLOAD EXAMIANS APP