Highway Engineering On a right angled road intersection with two way traffic, the total number of conflict points is 24 11 6 18 24 11 6 18 ANSWER DOWNLOAD EXAMIANS APP
Highway Engineering In case of hill roads, the extra widening is generally provided fully on the inner side of the curve fully on the outer side of the curve one-fourth on inner side and three-fourth on outer side of the curve equally on inner and outer sides of the curve fully on the inner side of the curve fully on the outer side of the curve one-fourth on inner side and three-fourth on outer side of the curve equally on inner and outer sides of the curve ANSWER DOWNLOAD EXAMIANS APP
Highway Engineering With increase in speed of the traffic stream, the minimum spacing of vehicles decreases first increases and then decreases after reaching a maximum value at optimum speed first decreases and then increases after reaching a minimum value at optimum speed increases decreases first increases and then decreases after reaching a maximum value at optimum speed first decreases and then increases after reaching a minimum value at optimum speed increases ANSWER DOWNLOAD EXAMIANS APP
Highway Engineering If the group index value of subgrade is between 5 and 9, then the subgrade is treated as fair very poor good poor fair very poor good poor ANSWER DOWNLOAD EXAMIANS APP
Highway Engineering For the design of super elevation for mixed traffic conditions, the speed is reduced by 15% 25% 20% 75% 15% 25% 20% 75% ANSWER DOWNLOAD EXAMIANS APP
Highway Engineering Which of the following premix methods is used for base course ? mastic asphalt bituminous bound macadam bituminous carpet sheet asphalt mastic asphalt bituminous bound macadam bituminous carpet sheet asphalt ANSWER DOWNLOAD EXAMIANS APP