Airport Engineering In an airport, if 4 groups of 5 gates each located well separated are considered for traffic and the future to present traffic ratio is 3, then the total requirement of future gates will be 36 68 32 44 36 68 32 44 ANSWER DOWNLOAD EXAMIANS APP
Airport Engineering For night landing, the thresholds are lighted White Green Yellow Red White Green Yellow Red ANSWER DOWNLOAD EXAMIANS APP
Airport Engineering For the proposed air port, the survey project provides Master plan All listed here Topographic plan Grading plan Master plan All listed here Topographic plan Grading plan ANSWER DOWNLOAD EXAMIANS APP
Airport Engineering The meteorological condition which influences the size and location of an air port is Reduced level All listed here Air density Atmosphere pressure Reduced level All listed here Air density Atmosphere pressure ANSWER DOWNLOAD EXAMIANS APP
Airport Engineering The lift off distance is the distance along the centre of the runway between the starting point and Point where air craft attains a height of 10.7 m End of the runway End of stop-way Point where air craft becomes air borne Point where air craft attains a height of 10.7 m End of the runway End of stop-way Point where air craft becomes air borne ANSWER DOWNLOAD EXAMIANS APP
Airport Engineering Assertion A : The ratio of arriving and departing aircrafts influences the airport capacity:Reason R : Landing operation is generally given priority over the taking off operation.Select your answer based on the coding system given below: Both A and R is true and R is the correct explanation of A A is true but R is false A is false but R is true Both A and R is true and R is not the correct explanation of A Both A and R is true and R is the correct explanation of A A is true but R is false A is false but R is true Both A and R is true and R is not the correct explanation of A ANSWER DOWNLOAD EXAMIANS APP