Consider a solar PV plant with the following specific conditions:
Analysis period: 1 year
Measured average solar irradiation intensity in 1 year: 150 kWh/m²
Generator area of the PV plant: 10 m² Efficiency factor of the PV modules: 15%
Electrical energy actually exported by plant to grid: 135 kWh
Calculate the performance ratio.

50%
60%
80%
75%

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP

MGVCL Exam Paper (30-07-2021 Shift 3)
Murray loop test is performed on a faulty cable 300 m long. At balance, the resistance connected to the faulty core was set at 20 Ω and the resistance of the resistor connected to the sound core was 40 Ω. Calculate the distance of the fault point from the test end.

200 m
400 m
100 m
300 m

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP