Construction Planning and Management Final technical authority of a project lies with Assistant Engineer Executive Engineer Chief Engineer Superintending Engineer Assistant Engineer Executive Engineer Chief Engineer Superintending Engineer ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Sensitivity analysis is a study of Change in output due to change in input Economics of cost and benefits of the project Comparison of profit and loss Comparison of assets and liabilities Change in output due to change in input Economics of cost and benefits of the project Comparison of profit and loss Comparison of assets and liabilities ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management In PERT analysis, the time estimates of activities and probability of their occurrence follow None of these Normal distribution curve Beta distribution curve Poisson's distribution curve None of these Normal distribution curve Beta distribution curve Poisson's distribution curve ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management In the given figure, the network of a project represents None of these Activity of an excavation which starts at event No. 1 and ends at even No. 2 Activity of an excavation of a footing Activity of excavation which takes 8 units of time None of these Activity of an excavation which starts at event No. 1 and ends at even No. 2 Activity of an excavation of a footing Activity of excavation which takes 8 units of time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following statements: In the bar chart planning 1. Interdependence of the operations cannot be portrayed. 2. Progress of work can be measured. 3. Spare time of the activities can be determined. 4. Schedule cannot be updated. 1, 2 and 4 are correct 1, 2 and 3 are correct 1 and 4 are correct 2, 3 and 4 are correct 1, 2 and 4 are correct 1, 2 and 3 are correct 1 and 4 are correct 2, 3 and 4 are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The first method invented for planning projects, was Programme Evaluation and Review Technique (PERT) Bar chart method Critical path method (CPM) Milestone chart Programme Evaluation and Review Technique (PERT) Bar chart method Critical path method (CPM) Milestone chart ANSWER DOWNLOAD EXAMIANS APP