Construction Planning and Management Final technical authority of a project lies with Assistant Engineer Superintending Engineer Executive Engineer Chief Engineer Assistant Engineer Superintending Engineer Executive Engineer Chief Engineer ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Rolling resistance of a wheel depends upon (i) Vehicle load (ii) Grade (iii) Ground conditions (i) and (ii) are correct (ii) and (iii) are correct (i) and (iii) are correct Only (i) is correct (i) and (ii) are correct (ii) and (iii) are correct (i) and (iii) are correct Only (i) is correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Sensitivity analysis is a study of Comparison of assets and liabilities Economics of cost and benefits of the project Comparison of profit and loss Change in output due to change in input Comparison of assets and liabilities Economics of cost and benefits of the project Comparison of profit and loss Change in output due to change in input ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The normal time required for the completion of project in the above problem is 9 days 19 days 14 days 13 days 9 days 19 days 14 days 13 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management In the time-cost optimisation, using CPM method for network analysis, the crashing of the activities along the critical path is done starting with the activity having Longest duration Highest cost slope Least cost slope Shortest duration Longest duration Highest cost slope Least cost slope Shortest duration ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Total float for any activity is defined as the difference between Its latest start time and earliest start time Its latest start time and earliest finish time Its latest finish time and earliest start time for its successor activity Its earliest finish time and earliest start time for its successor activity Its latest start time and earliest start time Its latest start time and earliest finish time Its latest finish time and earliest start time for its successor activity Its earliest finish time and earliest start time for its successor activity ANSWER DOWNLOAD EXAMIANS APP