Construction Planning and Management Final technical authority of a project lies with Assistant Engineer Superintending Engineer Chief Engineer Executive Engineer Assistant Engineer Superintending Engineer Chief Engineer Executive Engineer ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The time corresponding to minimum total project cost is Between normal time and crash time Crash time Optimistic time Normal time Between normal time and crash time Crash time Optimistic time Normal time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the total float and duration of an activity are 5 and 10 days respectively, the particular activity can be Performed at slower rate in 15 days Completed 5 days later All listed here Started 5 days later Performed at slower rate in 15 days Completed 5 days later All listed here Started 5 days later ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the expected time for completion of a project is 10 days with a standard deviation of 2 days, the expected time of completion of the project with 99.9% probability is 6 days 10 days 4 days 16 days 6 days 10 days 4 days 16 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following activities in a building construction: 1. Concreting of roof slabs 2. Brick-jelly lime concrete terracing 3. Erection of form work for slab 4. Construction of parapet wall in terrace The correct sequence of these activities is 3, 1, 4, 2 1, 3, 2, 4 3, 1, 2, 4 1, 3, 4, 2 3, 1, 4, 2 1, 3, 2, 4 3, 1, 2, 4 1, 3, 4, 2 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Assertion (A): Activity 57 is critical.Reason (R): Earliest finish time and latest finish time for events 57 are same R is correct but A is not correct Both A and R is correct A is correct but R is not correct Both A and R is incorrect R is correct but A is not correct Both A and R is correct A is correct but R is not correct Both A and R is incorrect ANSWER DOWNLOAD EXAMIANS APP