Construction Planning and Management Final technical authority of a project lies with Assistant Engineer Chief Engineer Superintending Engineer Executive Engineer Assistant Engineer Chief Engineer Superintending Engineer Executive Engineer ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the excavation of earth is done manually then it costs Rs. 10 per cum. A machine can excavate at a fixed cost of Rs. 4000 plus a variable cost of Rs. 2 per cum. The quantity of earth for which the cost of excavation by machine will be equal to the cost of manual excavation is 1000 cum 500 cum 1500 cum 2000 cum 1000 cum 500 cum 1500 cum 2000 cum ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management At a work site, statistical quality control of concrete means Measurement of risks to eliminate failures Reduction in costs for the removal of defects Applying the theory' of probability to sample testing or inspection Reduction in wastage of inspection costs Measurement of risks to eliminate failures Reduction in costs for the removal of defects Applying the theory' of probability to sample testing or inspection Reduction in wastage of inspection costs ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following activities in a building construction: 1. Concreting of roof slabs 2. Brick-jelly lime concrete terracing 3. Erection of form work for slab 4. Construction of parapet wall in terrace The correct sequence of these activities is 1, 3, 4, 2 3, 1, 4, 2 3, 1, 2, 4 1, 3, 2, 4 1, 3, 4, 2 3, 1, 4, 2 3, 1, 2, 4 1, 3, 2, 4 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Construction team means All listed here An architect An owner An engineer All listed here An architect An owner An engineer ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The probability of completion of any activity within its expected time is 0.999 1 0.841 0.5 0.999 1 0.841 0.5 ANSWER DOWNLOAD EXAMIANS APP