Construction Planning and Management Final technical authority of a project lies with Chief Engineer Executive Engineer Assistant Engineer Superintending Engineer Chief Engineer Executive Engineer Assistant Engineer Superintending Engineer ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Site order book is used for recording Instructions by the executive engineers Issue of store equipments Names of the casual labour Construction measurements Instructions by the executive engineers Issue of store equipments Names of the casual labour Construction measurements ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Mile Stone charts were invented in the year of 1920 1910 1930 1940 1920 1910 1930 1940 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The process of incorporating changes and rescheduling or replanning is called Resource levelling Updating Resource smoothening Critical path scheduling Resource levelling Updating Resource smoothening Critical path scheduling ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management In resources levelling Uniform demand of resources is achieved Total duration of project is reduced Cost of project is controlled Total duration of project is increased Uniform demand of resources is achieved Total duration of project is reduced Cost of project is controlled Total duration of project is increased ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the excavation of earth is done manually then it costs Rs. 10 per cum. A machine can excavate at a fixed cost of Rs. 4000 plus a variable cost of Rs. 2 per cum. The quantity of earth for which the cost of excavation by machine will be equal to the cost of manual excavation is 1500 cum 2000 cum 1000 cum 500 cum 1500 cum 2000 cum 1000 cum 500 cum ANSWER DOWNLOAD EXAMIANS APP