Construction Planning and Management Final technical authority of a project lies with Superintending Engineer Chief Engineer Assistant Engineer Executive Engineer Superintending Engineer Chief Engineer Assistant Engineer Executive Engineer ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The first method invented for planning projects, was Programme Evaluation and Review Technique (PERT) Bar chart method Milestone chart Critical path method (CPM) Programme Evaluation and Review Technique (PERT) Bar chart method Milestone chart Critical path method (CPM) ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the total float and duration of an activity are 5 and 10 days respectively, the particular activity can be All listed here Started 5 days later Completed 5 days later Performed at slower rate in 15 days All listed here Started 5 days later Completed 5 days later Performed at slower rate in 15 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which of the following earth moving machines has the shortest cycle time? Dipper shovel Hoe Drag line Clam shell Dipper shovel Hoe Drag line Clam shell ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The reduction in project time normally results in Increasing the direct cost and indirect cost both Decreasing the direct cost and indirect cost both Increasing the direct cost and decreasing the indirect cost Decreasing the direct cost and increasing indirect cost Increasing the direct cost and indirect cost both Decreasing the direct cost and indirect cost both Increasing the direct cost and decreasing the indirect cost Decreasing the direct cost and increasing indirect cost ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the excavation of earth is done manually then it costs Rs. 10 per cum. A machine can excavate at a fixed cost of Rs. 4000 plus a variable cost of Rs. 2 per cum. The quantity of earth for which the cost of excavation by machine will be equal to the cost of manual excavation is 1000 cum 2000 cum 1500 cum 500 cum 1000 cum 2000 cum 1500 cum 500 cum ANSWER DOWNLOAD EXAMIANS APP