Construction Planning and Management Final technical authority of a project lies with Chief Engineer Superintending Engineer Executive Engineer Assistant Engineer Chief Engineer Superintending Engineer Executive Engineer Assistant Engineer ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For a given activity, the optimistic time, pessimistic time and the most probable estimates are 5, 17 and 8 days respectively, The expected time is 8 days 10 days 15 days 9 days 8 days 10 days 15 days 9 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Economic saving of time results by crashing Cheapest critical activity Costliest noncritical activity Costliest critical activity Cheapest noncritical activity Cheapest critical activity Costliest noncritical activity Costliest critical activity Cheapest noncritical activity ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The critical activity has Minimum float None of these Zero float Maximum float Minimum float None of these Zero float Maximum float ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Assertion A: For a given depth of cut, the output of a power shovel can be increased by decreasing the angle of swing.Reason R: If the angle of swing is decreased, the cycle time will be decreased. Both A and R is true but R is not the correct explanation of A A is false but R is true Both A and R is true and R is the correct explanation of A A is true but R is false Both A and R is true but R is not the correct explanation of A A is false but R is true Both A and R is true and R is the correct explanation of A A is true but R is false ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The normal time required for the completion of project in the above problem is 19 days 14 days 9 days 13 days 19 days 14 days 9 days 13 days ANSWER DOWNLOAD EXAMIANS APP