Construction Planning and Management Final technical authority of a project lies with Superintending Engineer Executive Engineer Assistant Engineer Chief Engineer Superintending Engineer Executive Engineer Assistant Engineer Chief Engineer ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management An excavator costs Rs. 20,00,000 and has an estimated life of 8 years. It has no salvage value at the end of 8 years. The book value of the excavator at the end of 3 years using general double declining balance method is Rs. 8,43,750 Rs. 8,75,000 Rs. 11,56,250 Rs. 10,50,000 Rs. 8,43,750 Rs. 8,75,000 Rs. 11,56,250 Rs. 10,50,000 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For a given size of bucket, the ideal output of a dragline will be least in Good common earth Moist loam Wet sticky clay Sand and gravel Good common earth Moist loam Wet sticky clay Sand and gravel ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Whenever an activity has zero total float, then Independent float must be zero but free float need not be zero Free float and independent float both must be zero Free float of the activity must be zero but independent float need not be zero Free float and independent float both need not be zero Independent float must be zero but free float need not be zero Free float and independent float both must be zero Free float of the activity must be zero but independent float need not be zero Free float and independent float both need not be zero ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For the network shown in the given figure, the expected time for the activity 2-3 is 7 All listed here 1-2 is 4 3-4 is 8 2-3 is 7 All listed here 1-2 is 4 3-4 is 8 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which of the following is a weakness of bar chart? Interdependencies of activities All of these Uncertainties Project progress Interdependencies of activities All of these Uncertainties Project progress ANSWER DOWNLOAD EXAMIANS APP