Construction Planning and Management
Optimistic time, most likely time and pessimistic times for the activities of a network in the given figure are written above their arrows. If the contractual obligation time for the project is 75, the latest occurrence time for the event 2, is

20
15
35
25

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Output of a bulldozer is (i) Increased if drawbar HP of the tractor is increased for a given hauling distance (ii) Decreased if drawbar HP of the tractor is increased for a given hauling distance (iii) Increased if the hauling distance is increased for a given drawbar HP of the tractor (iv) Decreased if the hauling distance is increased for a given drawbar HP of the tractor

(i) and (iv) are correct
(ii) and (iii) are correct
(ii) and (iv) are correct
(i) and (iii) are correct

ANSWER DOWNLOAD EXAMIANS APP