Optimistic time, most likely time and pessimistic times for the activities of a network in the given figure are written above their arrows. If the contractual obligation time for the project is 75, the latest occurrence time for the event 2, is

20
15
35
25

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
If the optimistic time, most likely time and pessimistic time for activity A are 4, 6 and 8 respectively and for activity B are 5, 5.5 and 9 respectively, then

expected time of activity A is greater than the expected time of activity B
expected time of both activities A and B are same
expected time of activity B is greater than the expected time of activity A
None of these

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
At a work site, statistical quality control of concrete means

Reduction in costs for the removal of defects
Measurement of risks to eliminate failures
Applying the theory' of probability to sample testing or inspection
Reduction in wastage of inspection costs