MGVCL Exam Paper (30-07-2021 Shift 2)
In a power network, 400 kV is recorded at a 415 kV bus. A 50 MVAR, 415 kV shunt reactor is connected to the bus. What is the reactive power absorbed by the shunt reactor?

66.45 MVAR
76.45 MVAR
46.45 MVAR
56.45 MVAR

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP

MGVCL Exam Paper (30-07-2021 Shift 2)
A given solar cell has the following specifications:
Open-circuit voltage, Voc: 0.7 V
Short-circuit current, Isc: 3 A
Voltage at maximum power, Vmp: 0.5 V
Current at maximum power, Imp : 2.65 A
Calculate the fill factor.

1.23
1.58
0.81
0.63

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP

MGVCL Exam Paper (30-07-2021 Shift 2)
A three-phase, 12 kV, 50 Hz and 300 kW load is operating at 0.8 pf lag. If the pf is to be improved to unity, using star connected capacitor, the per phase value of the reactive VAR required is:

25 kVAR
50 kVAR
100 kVAR
75 kVAR

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP