Which one of the following statement with respect to Aerial Bunched Cables (ABC) system is TRUE?

The overall cost of the ABC system is very high as compared to the bare conductor system.
ABC system requires more clearance, insulators and high maintenance.
ABC system is not suitable for rural electrification which are situated in difficult terrain, hills, forests and coastal areas.
ABC system totally eliminates the fault on lines and thereby improving the quality of supply.

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP

MGVCL Exam Paper (30-07-2021 Shift 2)
The necessary equation to be solved during the load flow analysis using Fast-Decoupled method is given below:
where B' and B'' are formed using the imaginary part of the bus admittance matrix, Ybus. If the system consists of 6 buses of which one of the bus is slack bus and 2 bues are voltage regulated buses, then then the matrix B' is of order ____and the matrix B'' is of order____, respectivity.
∆P/|Vi| = - B'∆δ
∆Q/|Vi| = - B''∆|V|

3 and 6
5 and 3
3 and 5
6 and 3

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP

MGVCL Exam Paper (30-07-2021 Shift 2)
Interposing current-transformer (CT) is used in differential protection of a transformer to

match the standard ratio of CTs used on both sides of the transformer winding
limit the main CT secondary current
increase the sensitivity of the relay
minimize the effect of saturation of the main CTs

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP