Highway Engineering Equivalent factor of passenger car unit (PCU) for a passenger car as per IRC is 2.0 0.5 10 1.0 2.0 0.5 10 1.0 ANSWER DOWNLOAD EXAMIANS APP
Highway Engineering When the path travelled along the road surface is more than the circumferential movement of the wheels due to rotation, then it results in slipping turning skidding revolving slipping turning skidding revolving ANSWER DOWNLOAD EXAMIANS APP
Highway Engineering The particular places where pedestrians are to cross the pavement are properly marked by the pavement marking known as lane lines stop lines turn markings crosswalk lines lane lines stop lines turn markings crosswalk lines ANSWER DOWNLOAD EXAMIANS APP
Highway Engineering If the stopping distance and average length of a vehicle are 18 m and 6 m respectively, then the theoretical maxi¬mum capacity of a traffic lane at a speed of 10 m/sec is 3000 vehicles per hour 2000 vehicles per hour 1500 vehicles per hour 2500 vehicles per hour 3000 vehicles per hour 2000 vehicles per hour 1500 vehicles per hour 2500 vehicles per hour ANSWER DOWNLOAD EXAMIANS APP
Highway Engineering The direct interchange ramp involves diverging to the right side and merging from right diverging to the right side and merging from left diverging to the left side and merging from right diverging to the left side and merging from left diverging to the right side and merging from right diverging to the right side and merging from left diverging to the left side and merging from right diverging to the left side and merging from left ANSWER DOWNLOAD EXAMIANS APP
Highway Engineering Softening point of bitumen to be used for read construction at a place where maximum temperature is 40° C should be None of these equal to 40°C less-than 40°C greater than 40°C None of these equal to 40°C less-than 40°C greater than 40°C ANSWER DOWNLOAD EXAMIANS APP