GETCO Exam Paper (22-07-2015) During the insulation co-ordination in the sub station, the lowest insulation strength is at transformer bus bar CTs and PTs circuit breaker transformer bus bar CTs and PTs circuit breaker ANSWER DOWNLOAD EXAMIANS APP
GETCO Exam Paper (22-07-2015) When the load is suddenly increased in the receiving end of the system, the phase shift will remains same Not affected decrease increase remains same Not affected decrease increase ANSWER DOWNLOAD EXAMIANS APP
GETCO Exam Paper (22-07-2015) An over-current relay of current rating 5 A and setting 150% is connected to a 200/5 A CT. Then the relay to pickup, the line current required is 100 200 150 300 100 200 150 300 ANSWER DOWNLOAD EXAMIANS APP
GETCO Exam Paper (22-07-2015) Two watt meter method for 3 phase circuit is preferred over other methods because it can be used for balanced or unbalanced load all are correct PF of the load can also be estimated it can be used for star or delta connected load it can be used for balanced or unbalanced load all are correct PF of the load can also be estimated it can be used for star or delta connected load ANSWER DOWNLOAD EXAMIANS APP
GETCO Exam Paper (22-07-2015) In G-S method of power flow problem, the number of iterations _____ depends on tolerance depends on no of buses depends on voltage control buses remains fixed depends on tolerance depends on no of buses depends on voltage control buses remains fixed ANSWER DOWNLOAD EXAMIANS APP
GETCO Exam Paper (22-07-2015) HVDC transmission is preferred to EHV AC because VAR compensation is not required in it Its terminal equipment are inexpensive Harmonic problem is avoided System stability can be improved VAR compensation is not required in it Its terminal equipment are inexpensive Harmonic problem is avoided System stability can be improved ANSWER DOWNLOAD EXAMIANS APP