GETCO Exam Paper (22-07-2015) The power factor of the arc in circuit breaker is always leading always lagging always zero always unity always leading always lagging always zero always unity ANSWER DOWNLOAD EXAMIANS APP
GETCO Exam Paper (22-07-2015) Which of the following cable is extensively used for high tension and low tension work? PVC cable TRS cable VIR cable XLPE cable PVC cable TRS cable VIR cable XLPE cable ANSWER DOWNLOAD EXAMIANS APP
GETCO Exam Paper (22-07-2015) Critical clearing time of a fault in a power system is related to Transient stability limit Short circuit limit Reactive power limit Steady state limit Transient stability limit Short circuit limit Reactive power limit Steady state limit ANSWER DOWNLOAD EXAMIANS APP
GETCO Exam Paper (22-07-2015) Laplace transforms is used for for finding initial condition in a system converting non linear equation to linear equation finding transfer function of any systems converting diffential equation to algebraic equation for finding initial condition in a system converting non linear equation to linear equation finding transfer function of any systems converting diffential equation to algebraic equation ANSWER DOWNLOAD EXAMIANS APP
GETCO Exam Paper (22-07-2015) Fuel cell for power generation have drawback of _____ Synchronization problems Noise, pollution and maintenance problems Low life span Very high development costs Synchronization problems Noise, pollution and maintenance problems Low life span Very high development costs ANSWER DOWNLOAD EXAMIANS APP
GETCO Exam Paper (22-07-2015) The recent (as on 22/07/2015) Mahakumbh is held at Ujjain Nasik Haridwar Alahabad Ujjain Nasik Haridwar Alahabad ANSWER DOWNLOAD EXAMIANS APP