Construction Planning and Management Which of the following earth moving machines has the shortest cycle time? Clam shell Drag line Hoe Dipper shovel Clam shell Drag line Hoe Dipper shovel ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A tractor shovel has a purchase price of Rs. 4.7 lacs and could save the organization an amount of rupees one lac per year on operating costs. The salvage value after the amortization period is 10% of the purchase price. The capital recovery period will be 4.23 years 3.7 years 7.87 years 5 years 4.23 years 3.7 years 7.87 years 5 years ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Completion of an activity on CPM network diagram, is generally known Node Connector All listed here Event Node Connector All listed here Event ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Grader is used mainly for Finishing and shaping Trimming and finishing Shaping and trimming Finishing, shaping and trimming Finishing and shaping Trimming and finishing Shaping and trimming Finishing, shaping and trimming ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following activities in a building construction: 1. Concreting of roof slabs 2. Brick-jelly lime concrete terracing 3. Erection of form work for slab 4. Construction of parapet wall in terrace The correct sequence of these activities is 1, 3, 2, 4 3, 1, 2, 4 1, 3, 4, 2 3, 1, 4, 2 1, 3, 2, 4 3, 1, 2, 4 1, 3, 4, 2 3, 1, 4, 2 ANSWER DOWNLOAD EXAMIANS APP