Railway Engineering
Consider the following surveys. 1. Reconnaissance survey 2. Preliminary survey 3. Traffic survey 4. Location survey The correct sequence in which these surveys are conducted before the alignment of a track is finalised is

1,3,4,2
3,1,4,2
1,3,2,4
3,1,2,4

ANSWER DOWNLOAD EXAMIANS APP

Railway Engineering
On a single rail track, goods trains loaded with heavy iron material run starting from ‘A’ to ‘B’ and then empty wagons run from ‘B’ to ‘A’. The amount of creep in the rails:

Will be maximum at the middle of A and B
Will be more in the direction of A to B
Cannot be determined from the given data
Will be more in the direction of B to A

ANSWER DOWNLOAD EXAMIANS APP