Railway Engineering
Consider the following surveys. 1. Reconnaissance survey 2. Preliminary survey 3. Traffic survey 4. Location survey The correct sequence in which these surveys are conducted before the alignment of a track is finalised is

1,3,4,2
1,3,2,4
3,1,2,4
3,1,4,2