Building Construction In case of multi-storeyed buildings, the forms to be removed first are Column forms Sides of beams and girders All the above at the same time Bottom of beams and girders Column forms Sides of beams and girders All the above at the same time Bottom of beams and girders ANSWER DOWNLOAD EXAMIANS APP
Building Construction A concrete structure is set on fire and the temperature raises to 1000°C. The strength of concrete as compared to original strength reduces to 10 % 20 % 25 % 15 % 10 % 20 % 25 % 15 % ANSWER DOWNLOAD EXAMIANS APP
Building Construction The piece of a brick cut with its one corner equivalent to half the length and half the width of a full brick, is known as Bevelled closer Half king closer Queen closer King closer Bevelled closer Half king closer Queen closer King closer ANSWER DOWNLOAD EXAMIANS APP
Building Construction The arrangement made to support an unsafe structure temporarily, is known as Jacking Scaffolding Shoring Underpinning Jacking Scaffolding Shoring Underpinning ANSWER DOWNLOAD EXAMIANS APP
Building Construction The steel pile which is generally sunk in soft clay or loose sand of low bearing capacity, is Pipe pile Disc pile H-pile Screw pile Pipe pile Disc pile H-pile Screw pile ANSWER DOWNLOAD EXAMIANS APP