Process Equipment and Plant Design Baffle width is normally taken as __________ times the tank diameter. 0.2-0.45 0.4-0.5 0.1-0.12 0.45-0.6 0.2-0.45 0.4-0.5 0.1-0.12 0.45-0.6 ANSWER DOWNLOAD EXAMIANS APP
Process Equipment and Plant Design The raio, (properller agitator dia/tank dia) is normally taken as 0.15-030 0.5-0.65 0.60-0.90 0.75-0.85 0.15-030 0.5-0.65 0.60-0.90 0.75-0.85 ANSWER DOWNLOAD EXAMIANS APP
Process Equipment and Plant Design Baffle spacing is generally __________ the I.D. of the shell. Not greater than Both B and C Not less than one fifth of More than Not greater than Both B and C Not less than one fifth of More than ANSWER DOWNLOAD EXAMIANS APP
Process Equipment and Plant Design In a distillation column, minimum clearance to be maintained betweeen the overflow weir and the last row of the bubble caps is __________ cms. 2.5 20 15 7.5 2.5 20 15 7.5 ANSWER DOWNLOAD EXAMIANS APP
Process Equipment and Plant Design The thickness of segmental baffles (25 -35% cut truncated plates usually) is generally __________ the tube wall thickness. Half Equal to Twice Four times Half Equal to Twice Four times ANSWER DOWNLOAD EXAMIANS APP
Process Equipment and Plant Design Liquid/petroleum fuel storage tanks are built underground (as in case of petrol pumps), when the storage capacity is less than __________ kilolitres. 20 85 30 45 20 85 30 45 ANSWER DOWNLOAD EXAMIANS APP