Power Systems At slack bus, which one of the following combinations of variables is not specified? V and δ P and V P and Q Q and V V and δ P and V P and Q Q and V ANSWER DOWNLOAD EXAMIANS APP
Power Systems Under over excitation synchronous phase modifier works as any of the above shunt capacitor shunt reactor series capacitor any of the above shunt capacitor shunt reactor series capacitor ANSWER DOWNLOAD EXAMIANS APP
Power Systems The value of off diagonal elements is sum of admittances connected at bus j sum of admittances connected at bus i which is connected between bus i and bus j with positive sign which is connected between bus i and bus j with negative sign sum of admittances connected at bus j sum of admittances connected at bus i which is connected between bus i and bus j with positive sign which is connected between bus i and bus j with negative sign ANSWER DOWNLOAD EXAMIANS APP
Power Systems A 25 MVA, 11 kV alternator is supplying full load at a point of 0.75 lagging. Determine the percentage increase in earning capacity when it is operated at improved power factor of 0.96 lagging. None of above 28 %. 56 %. 14 %. None of above 28 %. 56 %. 14 %. ANSWER DOWNLOAD EXAMIANS APP
Power Systems A fault occurring at the terminals of an unloaded synchronous generator operating at its rated voltage has resulted in the following values of currents and voltages. IR0 = j 2.37 pu IR1 = -j 3.05 pu IR2 = j 0.68 pu VR0 = VR1 = VR2 = 0.237 pu. Which of the following faults has occurred? LG LLL LL LLG LG LLL LL LLG ANSWER DOWNLOAD EXAMIANS APP
Power Systems In an induction relay for a particular current setting the operating time 4 sec. When the time multiplier setting is 0.8 if the time multiplier setting is rest to 1 the operating time is 5. 10. un changed. 1. 5. 10. un changed. 1. ANSWER DOWNLOAD EXAMIANS APP