Highway Engineering
For the construction of water bound macadam roads, the correct sequence of operations after spreading coarse aggregates is

dry rolling, application of screening, application of filler and wet rolling
dry rolling, application of screening, wet rolling and application of filler
dry rolling, wet rolling, application of screening and application of filler
dry rolling, application of filler, wet rolling and application of screening

ANSWER DOWNLOAD EXAMIANS APP

Highway Engineering
Length of a vehicle affects

width of shoulders and parking facilities
extra width of pavement and minimum turning radius
clearance to be provided under structures such as overbridges, under-bridges etc.
width of traffic lanes

ANSWER DOWNLOAD EXAMIANS APP

Highway Engineering
Select the correct statement.

Minimum and maximum values of group index can be 0 and 20 respectively
All of these
More the value of group index, less thickness of pavement will be required
More the value of CBR, greater thickness of pavement will be required