Railway Engineering A train is hauled by 4-8-2 locomotive. The number of driving wheels in this locomotive is 16 8 12 4 16 8 12 4 ANSWER DOWNLOAD EXAMIANS APP
Railway Engineering Number offish bolts per fish plate is 5 4 6 2 5 4 6 2 ANSWER DOWNLOAD EXAMIANS APP
Railway Engineering Consider the following surveys.1. Reconnaissance survey2. Preliminary survey3. Traffic survey4. Location surveyThe correct sequence in which these surveys are conducted before the alignment of a track is finalised is 1,3,4,2 3,1,4,2 3,1,2,4 1,3,2,4 1,3,4,2 3,1,4,2 3,1,2,4 1,3,2,4 ANSWER DOWNLOAD EXAMIANS APP
Railway Engineering Lead of crossing is the distance from the toe of the switch to the theoretical nose of crossing heel of the switch to the toe of the switch toe of the switch to the actual nose of crossing heel of the switch to the theoretical nose of the crossing toe of the switch to the theoretical nose of crossing heel of the switch to the toe of the switch toe of the switch to the actual nose of crossing heel of the switch to the theoretical nose of the crossing ANSWER DOWNLOAD EXAMIANS APP
Railway Engineering The sleepers resting directly on girder are fastened to the top flange of girder by rail screws dog spikes fang bolts hook bolts rail screws dog spikes fang bolts hook bolts ANSWER DOWNLOAD EXAMIANS APP
Railway Engineering When the rail ends rest on a joint sleeper, the joint is termed as bridge joint suspended rail joint base joint supported rail joint bridge joint suspended rail joint base joint supported rail joint ANSWER DOWNLOAD EXAMIANS APP