MGVCL Exam Paper (30-07-2021 Shift 2)
A 1000 kVA ONAN cooled transformer has a load of 500 kVA throughout the day except for a period of 4 hours. What is the permissible overload for a duration of four hours. Assume the permissible load kVA as a fraction of rated kVA is 1.24.

2480 kVA
620 kVA
930 kVA
1240 kVA

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP

MGVCL Exam Paper (30-07-2021 Shift 2)
The expression for voltage regulation of a short transmission line for leading power factor is given by: ____, where, 'I' is the line current, 'V_r' is the receiving end voltage, 'R' is the line resitance and 'X' is the line reactance.

(IRcosφ_r + IXsinφ_r)/V_r
(IXcosφ_r - IRsinφ_r)/V_r
(IRcosφ_r - IXsinφ_r)/V_r
(IXcosφ_r + IRsinφ_r)/V_r

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP

MGVCL Exam Paper (30-07-2021 Shift 2)
A three-phase, 12 kV, 50 Hz and 300 kW load is operating at 0.8 pf lag. If the pf is to be improved to unity, using star connected capacitor, the per phase value of the reactive VAR required is:

25 kVAR
50 kVAR
100 kVAR
75 kVAR

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP

MGVCL Exam Paper (30-07-2021 Shift 2)
In a single phase energy meter, the shunt electromagnet is energized by a ____of ____

current coil, thin wire of more turns
pressure coil, thin wire of more turns
pressure coil, thick wire of few turns
current coil, thick wire of few turns

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP

MGVCL Exam Paper (30-07-2021 Shift 2)
Which one of the following statement with respect to Aerial Bunched Cables (ABC) system is TRUE?

ABC system totally eliminates the fault on lines and thereby improving the quality of supply.
ABC system requires more clearance, insulators and high maintenance.
The overall cost of the ABC system is very high as compared to the bare conductor system.
ABC system is not suitable for rural electrification which are situated in difficult terrain, hills, forests and coastal areas.

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP