MGVCL Exam Paper (30-07-2021 Shift 2)
A 1000 kVA ONAN cooled transformer has a load of 500 kVA throughout the day except for a period of 4 hours. What is the permissible overload for a duration of four hours. Assume the permissible load kVA as a fraction of rated kVA is 1.24.

930 kVA
1240 kVA
2480 kVA
620 kVA

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP

MGVCL Exam Paper (30-07-2021 Shift 2)
A three-phase, 12 kV, 50 Hz and 300 kW load is operating at 0.8 pf lag. If the pf is to be improved to unity, using star connected capacitor, the per phase value of the reactive VAR required is:

50 kVAR
25 kVAR
75 kVAR
100 kVAR

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP

MGVCL Exam Paper (30-07-2021 Shift 2)
A generating station having 'n' section busbars each rated at Q kVA with ×% reactance is connected on the tie-bars systems through busbar reactances of b%. Determine the short circuit kVA if a 3-phase fault takes place on one section.

Q[(1/x) + (n+1)/(bn-x)]
Q[(1/x) + (n-1)/(bn+x)]
Q[(1/x) - (n+1)/(bn-x)]
Q[(1/x) + (n+1)/(bn+x)]

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP

MGVCL Exam Paper (30-07-2021 Shift 2)
Which one of the following statement with respect to Aerial Bunched Cables (ABC) system is TRUE?

ABC system requires more clearance, insulators and high maintenance.
The overall cost of the ABC system is very high as compared to the bare conductor system.
ABC system totally eliminates the fault on lines and thereby improving the quality of supply.
ABC system is not suitable for rural electrification which are situated in difficult terrain, hills, forests and coastal areas.

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP