MGVCL Exam Paper (30-07-2021 Shift 2)
In the context of smart meters, the term 'SMETS' stand for

Smart Metering Equipment Technical Specifications
Smart Monitoring Equipment Technical Specifications
Standard Metering Equipment Technical Specifications
Standard Monitoring Equipment Technical Specifications

ANSWER DOWNLOAD EXAMIANS APP

MGVCL Exam Paper (30-07-2021 Shift 2)
A 3-phase motor load has a p.f. of 0.397 lagging. The two wattmeter method used to measure power show the input as 30 kW. Find the reading on each wattmeter.

W1 = 10 kW and W2 = 20 kW
W1 = 5 kW and W2 = 25 kW
W1 = -5 kW and W2 = 35 kW
W1 = -10 kW and W2 = 40 kW

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP

MGVCL Exam Paper (30-07-2021 Shift 2)
In a power network, 400 kV is recorded at a 415 kV bus. A 50 MVAR, 415 kV shunt reactor is connected to the bus. What is the reactive power absorbed by the shunt reactor?

56.45 MVAR
46.45 MVAR
66.45 MVAR
76.45 MVAR

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP