Railway Engineering Width of ballast section for Broad Gauge is 4.30 m 2.25 m 1.83 m 3.35 m 4.30 m 2.25 m 1.83 m 3.35 m ANSWER DOWNLOAD EXAMIANS APP
Railway Engineering Which of the following factors govern the choice of the gauge ? i) volume and nature of traffic ii) speed of train iii) physical features of the country The correct answer is only (i) (i), (ii) and (iii) both (i) and (ii) both (ii) and (iii) only (i) (i), (ii) and (iii) both (i) and (ii) both (ii) and (iii) ANSWER DOWNLOAD EXAMIANS APP
Railway Engineering Consider the following surveys.1. Reconnaissance survey2. Preliminary survey3. Traffic survey4. Location surveyThe correct sequence in which these surveys are conducted before the alignment of a track is finalised is 3,1,2,4 3,1,4,2 1,3,4,2 1,3,2,4 3,1,2,4 3,1,4,2 1,3,4,2 1,3,2,4 ANSWER DOWNLOAD EXAMIANS APP
Railway Engineering Metal sleepers are superior to wooden sleepers with respect to fastening life cost track circuiting fastening life cost track circuiting ANSWER DOWNLOAD EXAMIANS APP
Railway Engineering In a scissors cross-over, the crossings provided are i) 2 obtuse angle crossings ii) 4 obtuse angle crossings iii) 4 acute angle crossings iv) 6 acute angle crossings The correct answer is (ii) and (iii) (i) and (iii) (i)and(iv) (ii) and (iv) (ii) and (iii) (i) and (iii) (i)and(iv) (ii) and (iv) ANSWER DOWNLOAD EXAMIANS APP
Railway Engineering Number of keys used in CST-9 sleeper is 4 None of these 2 3 4 None of these 2 3 ANSWER DOWNLOAD EXAMIANS APP