MGVCL Exam Paper (30-07-2021 Shift 2)
Which of the following does the term 'feeder automation' include?

automatic reclosing
All of these
feeder remote point voltage control
substation reactive power control

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP

MGVCL Exam Paper (30-07-2021 Shift 2)
If no load is connected to solar PV system,

it will dissipate energy in the panel and increase its temperature
it will start reflecting the light
it will stop absorbing light
its voltage will go on increasing till its breakdown

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP

MGVCL Exam Paper (30-07-2021 Shift 2)
A 3-phase motor load has a p.f. of 0.397 lagging. The two wattmeter method used to measure power show the input as 30 kW. Find the reading on each wattmeter.

W1 = -10 kW and W2 = 40 kW
W1 = 10 kW and W2 = 20 kW
W1 = 5 kW and W2 = 25 kW
W1 = -5 kW and W2 = 35 kW

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP

MGVCL Exam Paper (30-07-2021 Shift 2)
A three-phase, 12 kV, 50 Hz and 300 kW load is operating at 0.8 pf lag. If the pf is to be improved to unity, using star connected capacitor, the per phase value of the reactive VAR required is:

75 kVAR
100 kVAR
50 kVAR
25 kVAR

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP

MGVCL Exam Paper (30-07-2021 Shift 2)
Which one of the following statement is TRUE?

In the cables, sheaths are used to provide enough strength.
In the cables, the location of fault is usually found out by comparing the capacitances of insulated conductors.
The current carrying capacity of cables in DC is less than that in AC.
Underground cables are laid at sufficient depth to avoid being unearthed easily due to removal of soil.

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP