MGVCL Exam Paper (30-07-2021 Shift 2)
Which of the following does the term 'feeder automation' include?

automatic reclosing
feeder remote point voltage control
substation reactive power control
All of these

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP

MGVCL Exam Paper (30-07-2021 Shift 2)
The magnitude of the generator earth-fault current is limited by

controlling field exciter
using higher rating CTs
inserting suitable resistance in neutral grounding circuit
inserting the stabilizing resistance in series with the relay

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP

MGVCL Exam Paper (30-07-2021 Shift 2)
A power factor less than unity results in which of the following disadvantages?
(i) Large kVA rating of equipment
(ii)Poor voltage regulation
(iii) Greater conductor size

(i) and (iii) only
(i), (ii) and (iii)
(ii) and (iii) only
(i) and (ii) only

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP

MGVCL Exam Paper (30-07-2021 Shift 2)
The expression for voltage regulation of a short transmission line for leading power factor is given by: ____, where, 'I' is the line current, 'V_r' is the receiving end voltage, 'R' is the line resitance and 'X' is the line reactance.

(IRcosφ_r + IXsinφ_r)/V_r
(IRcosφ_r - IXsinφ_r)/V_r
(IXcosφ_r - IRsinφ_r)/V_r
(IXcosφ_r + IRsinφ_r)/V_r

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP

MGVCL Exam Paper (30-07-2021 Shift 2)
In a short circuit test on circuit breaker, time to reach the peak re-striking voltage is 50 µs with the peak restriking voltage of 100 kV. Determine average RRRV (Rate of rise re-striking voltage)?

1 x 10⁶ kV/sec
3 x 10⁶ kV/sec
4 x 10⁶ kV/sec
2 x 10⁶ kV/sec

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP