At no load the solar cell will be operating in open circuit condition. If there is internal shunting resistance it will slightly load the solar cell. This shunt resistance must be high enough such that it will not cause an appreciable loss of the photo voltaic power.
The capacity of reactor = 50 MVAr when it is operated at 415 kV. Impedance of reactor = V2/MVAr = (415*415)2/50 = 3444.5 Ω For 400 kV, Reactive power observed = (400*400)/3444.5 = 46.45 MVAR
Or
VAr capacity of capacitor or reactor is proportional to V²
Buchholz relay is gas operated relay. It will operate when internal fault occurs in transformer. It is placed between tank to main conservator. It has two contacts trip and alarm. Use of Buchholz relay in distribution transformer is not economical.