MGVCL Exam Paper (30-07-2021 Shift 2)
If no load is connected to solar PV system,

it will start reflecting the light
it will stop absorbing light
it will dissipate energy in the panel and increase its temperature
its voltage will go on increasing till its breakdown

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP

MGVCL Exam Paper (30-07-2021 Shift 2)
In the context of smart meters, the term 'SMETS' stand for

Standard Metering Equipment Technical Specifications
Smart Metering Equipment Technical Specifications
Smart Monitoring Equipment Technical Specifications
Standard Monitoring Equipment Technical Specifications

ANSWER DOWNLOAD EXAMIANS APP

MGVCL Exam Paper (30-07-2021 Shift 2)
The magnitude of the generator earth-fault current is limited by

inserting suitable resistance in neutral grounding circuit
controlling field exciter
inserting the stabilizing resistance in series with the relay
using higher rating CTs

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP

MGVCL Exam Paper (30-07-2021 Shift 2)
A power factor less than unity results in which of the following disadvantages?
(i) Large kVA rating of equipment
(ii)Poor voltage regulation
(iii) Greater conductor size

(i), (ii) and (iii)
(i) and (ii) only
(i) and (iii) only
(ii) and (iii) only

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP

MGVCL Exam Paper (30-07-2021 Shift 2)
શિક્ષકે વિદ્યાર્થીને વાર્તા કહી'
1. વાક્ય અક્મર્ક છે.
2. વાક્ય દ્રીકર્મક છે.
3. વાક્યમાં વિદ્યાર્થીને 'પ્રધાન કર્મ' છે અને વાર્તા 'ગૌણ કર્મ' છે.
4.વાક્યમાં વાર્તાને 'પ્રધાન કર્મ' છે અને વિધાથીને 'ગૌણ કર્મ' છે

2,4
2,3
1,3
1,3

ANSWER DOWNLOAD EXAMIANS APP