MGVCL Exam Paper (30-07-2021 Shift 2)
If no load is connected to solar PV system,

it will start reflecting the light
it will stop absorbing light
it will dissipate energy in the panel and increase its temperature
its voltage will go on increasing till its breakdown

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP

MGVCL Exam Paper (30-07-2021 Shift 2)
Which of the following is true regarding access lists applied to an interface?

You can apply two access lists to any interface
You can place as many access lists as you want on any interface until you run out of memory.
You can apply only one access list on any interface
One access list may be configured, per direction, for each layer 3 protocol configured on an interface

ANSWER DOWNLOAD EXAMIANS APP

MGVCL Exam Paper (30-07-2021 Shift 2)
A three-phase, 12 kV, 50 Hz and 300 kW load is operating at 0.8 pf lag. If the pf is to be improved to unity, using star connected capacitor, the per phase value of the reactive VAR required is:

50 kVAR
75 kVAR
25 kVAR
100 kVAR

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP