MGVCL Exam Paper (30-07-2021 Shift 3)
Which among these components connects to physical equipments of the distribution system?

Communication infrastructure
Remote Terminal Unit
Central control room with host computers
None of these

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP

MGVCL Exam Paper (30-07-2021 Shift 3)
Murray loop test is performed on a faulty cable 300 m long. At balance, the resistance connected to the faulty core was set at 20 Ω and the resistance of the resistor connected to the sound core was 40 Ω. Calculate the distance of the fault point from the test end.

100 m
300 m
400 m
200 m