Power Systems
When is the ferranti effect on long overhead lines experienced?

 The line is lightly loaded
 The line is heavily loaded
 The line is fully loaded
 The power factor is unity

ANSWER DOWNLOAD EXAMIANS APP

Power Systems
In order to have lower cost of power generaion

 the load factor should be high but diversity factor should be low
 the load factor and diversity factor should be low
 the load factor should be low but diversity factor should be high
 The load factor and diversity factor should be high

ANSWER DOWNLOAD EXAMIANS APP