Process Equipment and Plant Design Wall thickness of schedule 40 pipe as compared to that of schedule 80 pipe is Same Less More Cither A or B; depends upon the I.D. of the pipe Same Less More Cither A or B; depends upon the I.D. of the pipe ANSWER DOWNLOAD EXAMIANS APP
Process Equipment and Plant Design The most common standard size of bubble caps used in industrial operation is 4" dia cap with 8" dia riser 8" dia cap with 1" dia riser 1" dia cap with 0.5" dia riser 6" dia cap with 4" dia riser 4" dia cap with 8" dia riser 8" dia cap with 1" dia riser 1" dia cap with 0.5" dia riser 6" dia cap with 4" dia riser ANSWER DOWNLOAD EXAMIANS APP
Process Equipment and Plant Design Number of evaporators which can be used in service in a multiple effect evaporation system is limited by the Both A & B Practical limit reached, due to low heat transfer rate because of inadequate temperature difference Neither A nor B Economic limit reached, when the plant cost exceeds the saving of steam Both A & B Practical limit reached, due to low heat transfer rate because of inadequate temperature difference Neither A nor B Economic limit reached, when the plant cost exceeds the saving of steam ANSWER DOWNLOAD EXAMIANS APP
Process Equipment and Plant Design In the design of a bag filter, the gas temperature is an important consideration, as it affects the Gas density All of these Fibre selection Gas viscosity Gas density All of these Fibre selection Gas viscosity ANSWER DOWNLOAD EXAMIANS APP
Process Equipment and Plant Design Log mean temperature difference in case of multi-pass shell and tube heat exchanger is always More than arithmetic mean value More than geometric mean value Less than arithmetic mean value Both B & C More than arithmetic mean value More than geometric mean value Less than arithmetic mean value Both B & C ANSWER DOWNLOAD EXAMIANS APP
Process Equipment and Plant Design Optimum reflux ratio in a continuous distillation column is determined by the Total cost consideration (fixed cost of the column plus the cooling water & steam cost) None of these Maximum permissible vapour velocity Flooding limit of the column Total cost consideration (fixed cost of the column plus the cooling water & steam cost) None of these Maximum permissible vapour velocity Flooding limit of the column ANSWER DOWNLOAD EXAMIANS APP