Building Construction The window which is provided on a sloping roof of a building, is called Lantern window Dormer window Louvered window Rash window Lantern window Dormer window Louvered window Rash window ANSWER DOWNLOAD EXAMIANS APP
Building Construction The bond in which headers and stretchers are laid in alternate courses and every stretcher course is started with a three fourth brick bat, is known as Monk bond Dutch bond Rat-trap bond English cross bond Monk bond Dutch bond Rat-trap bond English cross bond ANSWER DOWNLOAD EXAMIANS APP
Building Construction In English garden wall bond One course of headers to three or five course of stretchers The middle course of stretchers is started with a header to give proper vertical joints All of these Queen closer in provided in each heading course One course of headers to three or five course of stretchers The middle course of stretchers is started with a header to give proper vertical joints All of these Queen closer in provided in each heading course ANSWER DOWNLOAD EXAMIANS APP
Building Construction The vertical posts placed at the top and bottom ends of a flight supporting the hand rail are known as Balusters Newel posts Railings Balustrades Balusters Newel posts Railings Balustrades ANSWER DOWNLOAD EXAMIANS APP
Building Construction Which one of the following activities is not correct as applicable to brick corbels The maximum projection of the corbel should not be more than the thickness of the wall Stretcher bond is generally used for the construction of brick corbel The maximum projection of each corbel course should be limited to a quarter brick at a time The discontinuous corbels are used to carry heavy concentrated loads The maximum projection of the corbel should not be more than the thickness of the wall Stretcher bond is generally used for the construction of brick corbel The maximum projection of each corbel course should be limited to a quarter brick at a time The discontinuous corbels are used to carry heavy concentrated loads ANSWER DOWNLOAD EXAMIANS APP
Building Construction For providing a raft foundation, the following activities are involved1.Ramming the foundation bed2.Excavation of the soil upto required depth3.Laying the reinforcement over the foundation bed4.Curing the cement concrete placed over reinforcement5.Pouring the cement concrete over the reinforcementThe correct sequence is 1, 2, 3, 4, 5 3, 2, 5, 1, 4 5, 4, 3, 2, 1 2, 1, 3, 5, 4 1, 2, 3, 4, 5 3, 2, 5, 1, 4 5, 4, 3, 2, 1 2, 1, 3, 5, 4 ANSWER DOWNLOAD EXAMIANS APP