Building Construction The type of arch used for high class buildings where appearance is of prime importance, is known as Gauged brick arch Ashlar arch Rubble arch Axed brick arch Gauged brick arch Ashlar arch Rubble arch Axed brick arch ANSWER DOWNLOAD EXAMIANS APP
Building Construction For the construction of flyovers in sandy soils, the type of foundation provided, is Raft footing Pier footing Combined footing Strap footing Raft footing Pier footing Combined footing Strap footing ANSWER DOWNLOAD EXAMIANS APP
Building Construction The members which support covering material of a sloping roof, are Battens Rafters Purlins Struts Battens Rafters Purlins Struts ANSWER DOWNLOAD EXAMIANS APP
Building Construction The maximum number of steps in a flight should generally be restricted to 15 10 12 No limit 15 10 12 No limit ANSWER DOWNLOAD EXAMIANS APP
Building Construction The maximum permissible differential settlement, in case of foundations in clayey soil, is usually limited to 10 mm 20 mm 30 mm 40 mm 10 mm 20 mm 30 mm 40 mm ANSWER DOWNLOAD EXAMIANS APP
Building Construction The raft slab is projected beyond the outer walls of the structure by 15 to 20 cm 30 to 45 cm 5 to 10 cm 25 to 30 cm 15 to 20 cm 30 to 45 cm 5 to 10 cm 25 to 30 cm ANSWER DOWNLOAD EXAMIANS APP