Building Construction
In ordinary residential and public buildings, the damp proof course is generally provided at

Plinth level
Water table level
Midway ground level and water-table level
Ground level

ANSWER DOWNLOAD EXAMIANS APP

Building Construction
In the method of tube boring of soil investigation, the following is essential:

A tube of about 2 meters length and 20 cm diameter with a cutting edge
All listed here
The tube is raised and lowered by 4 thick rope moving over a pulley suspended on a tripod stand
A flap valve at the bottom of tube is provided to extract the soil sample

ANSWER DOWNLOAD EXAMIANS APP