Building Construction The art of bringing the floor to a true level surface by means of screeds, is called None of these Topping Bedding Screeding None of these Topping Bedding Screeding ANSWER DOWNLOAD EXAMIANS APP
Building Construction The skirting/dado in a bath roof should be upto Ceiling Level of the tap 15 cm above floor level 200 cm Ceiling Level of the tap 15 cm above floor level 200 cm ANSWER DOWNLOAD EXAMIANS APP
Building Construction In case of foundations on sandy soil, maximum permissible differential settlement, is usually limited to 25 mm 45 mm 15 mm 35 mm 25 mm 45 mm 15 mm 35 mm ANSWER DOWNLOAD EXAMIANS APP
Building Construction Rotary drilling Hinders the ground water observations and permeability test Is not suitable for deposits containing very coarse gravel Is not economical for holes of less than 10 cm All listed here Hinders the ground water observations and permeability test Is not suitable for deposits containing very coarse gravel Is not economical for holes of less than 10 cm All listed here ANSWER DOWNLOAD EXAMIANS APP
Building Construction The type of footing which is used to transmit heavy loads through steel columns is Isolated footing Grillage foundation Well foundation Raft foundation Isolated footing Grillage foundation Well foundation Raft foundation ANSWER DOWNLOAD EXAMIANS APP
Building Construction To ensure that supporting area of an offset footing of a boundary wall is fully compressive, the C.G. of load must act Within the middle fifth of the base Neither (A), (B) nor (C) At the centre of the base Within the middle third of the base Within the middle fifth of the base Neither (A), (B) nor (C) At the centre of the base Within the middle third of the base ANSWER DOWNLOAD EXAMIANS APP