Building Construction The method of moving each brick through a small horizontal distance before it is finally laid in any brick wall and pressing it by means of brick hammer, is known as Laying Grouting Troweling Placing Laying Grouting Troweling Placing ANSWER DOWNLOAD EXAMIANS APP
Building Construction A floor constructed with the 4 to 6 mm marble chips, is known Marble floor Reinforced marble floor Terrazzo floor Chip floor Marble floor Reinforced marble floor Terrazzo floor Chip floor ANSWER DOWNLOAD EXAMIANS APP
Building Construction For a rectangular foundation of width b, eccentricity of load should not exceed b/6 b/2 b/3 b/4 b/6 b/2 b/3 b/4 ANSWER DOWNLOAD EXAMIANS APP
Building Construction The form Work including the props can be removed from beams, only after 7 days 21 days 14 days 3 days 7 days 21 days 14 days 3 days ANSWER DOWNLOAD EXAMIANS APP
Building Construction The opening provided in sloping roof with its top parallel to the roof surface, is called Sky light window Dormer window Lantern window Louvered window Sky light window Dormer window Lantern window Louvered window ANSWER DOWNLOAD EXAMIANS APP
Building Construction The depth of excavation of foundations, is generally measured with a Steel tape Levelling staff Ranging rod Boning rod Steel tape Levelling staff Ranging rod Boning rod ANSWER DOWNLOAD EXAMIANS APP