Building Construction The angle between skew back of a flat arch and the horizontal, is kept approximately equal to 30° 0° 90° 60° 30° 0° 90° 60° ANSWER DOWNLOAD EXAMIANS APP
Building Construction A solid core of rock is formed inside the cylinder in the case of Auger boring Percussion drilling Wash boring Diamond drilling Auger boring Percussion drilling Wash boring Diamond drilling ANSWER DOWNLOAD EXAMIANS APP
Building Construction In places where the soil is soft and has small resistance to the flow of concrete, which one of the following types of piles, is used Vibro pile Franki pile Pedestal pile Pressure pile Vibro pile Franki pile Pedestal pile Pressure pile ANSWER DOWNLOAD EXAMIANS APP
Building Construction The construction joints in buildings are provided after 20 m 10 m 15 m 40 m 20 m 10 m 15 m 40 m ANSWER DOWNLOAD EXAMIANS APP
Building Construction The lower edge of the pitched roof, from where the rain water of the roof surface drops down, is known as Hip Eaves Gable Ridge Hip Eaves Gable Ridge ANSWER DOWNLOAD EXAMIANS APP
Building Construction The form work from the sides of beams can be removed only after 4 days 14 days 7 days 1 day 4 days 14 days 7 days 1 day ANSWER DOWNLOAD EXAMIANS APP