Building Construction The range of spread from the wall base to outer edge of a brick work foundation does not exceed 1/2 horizontal to 1 vertical 1 horizontal to 1 vertical 2/3 horizontal to 1 vertical 2 horizontals to 1 vertical 1/2 horizontal to 1 vertical 1 horizontal to 1 vertical 2/3 horizontal to 1 vertical 2 horizontals to 1 vertical ANSWER DOWNLOAD EXAMIANS APP
Building Construction The bond in which headers and stretchers are laid in alternate courses and every stretcher course is started with a three fourth brick bat, is known as English cross bond Rat-trap bond Monk bond Dutch bond English cross bond Rat-trap bond Monk bond Dutch bond ANSWER DOWNLOAD EXAMIANS APP
Building Construction Negative skin friction Neither (A) not (B) Is a downward drag acting on a pile due to downward movement of the surrounding compressible soil relative to the pile Both (A) and (B) Develops due to lowering of ground water Neither (A) not (B) Is a downward drag acting on a pile due to downward movement of the surrounding compressible soil relative to the pile Both (A) and (B) Develops due to lowering of ground water ANSWER DOWNLOAD EXAMIANS APP
Building Construction The vertical members fixed between steps and hand rail, are known Newel posts Balusters Strings Soffits Newel posts Balusters Strings Soffits ANSWER DOWNLOAD EXAMIANS APP
Building Construction Depth or height of the arch is the Vertical distance between springing line and intrados Perpendicular distance between intrados and extrados Perpendicular distance between springing line and extrados None of these Vertical distance between springing line and intrados Perpendicular distance between intrados and extrados Perpendicular distance between springing line and extrados None of these ANSWER DOWNLOAD EXAMIANS APP
Building Construction If height of the first storey of a building is 3.2 m and riser is 13 cm, the number of treads required, is 25 12 24 18 25 12 24 18 ANSWER DOWNLOAD EXAMIANS APP