Building Construction The taper of precast concrete pile should not be more than 4 cm per metre length 2 cm per metre length 5 cm per metre length 1 cm per metre length 4 cm per metre length 2 cm per metre length 5 cm per metre length 1 cm per metre length ANSWER DOWNLOAD EXAMIANS APP
Building Construction The process of keeping concrete moist for a certain period after its finishing, is known as Compaction of concrete Finishing of concrete Placing of concrete Curing of concrete Compaction of concrete Finishing of concrete Placing of concrete Curing of concrete ANSWER DOWNLOAD EXAMIANS APP
Building Construction Minimum width of landing should be Half the width of stairs Twice the width of stairs Equal to width of stairs One fourth the width of stairs Half the width of stairs Twice the width of stairs Equal to width of stairs One fourth the width of stairs ANSWER DOWNLOAD EXAMIANS APP
Building Construction The portion of a brick cut across the width, is called Bat Bed Closer Half brick Bat Bed Closer Half brick ANSWER DOWNLOAD EXAMIANS APP
Building Construction The width of the hollow space between two walls of a cavity wall should not exceed 15 cm 7.5 cm 10 cm 5 cm 15 cm 7.5 cm 10 cm 5 cm ANSWER DOWNLOAD EXAMIANS APP
Building Construction The highest line of sloping roof, where two opposite slopes meet, is known as Ridge Rafter Eave Crown Ridge Rafter Eave Crown ANSWER DOWNLOAD EXAMIANS APP