Building Construction The taper of precast concrete pile should not be more than 2 cm per metre length 4 cm per metre length 1 cm per metre length 5 cm per metre length 2 cm per metre length 4 cm per metre length 1 cm per metre length 5 cm per metre length ANSWER DOWNLOAD EXAMIANS APP
Building Construction A cut in frame of a door to receive the shutter, is called Rebate Louver Horn Stop Rebate Louver Horn Stop ANSWER DOWNLOAD EXAMIANS APP
Building Construction The loose pockets in soil mass can be bridged safely by providing a raft foundation provided the soft area is smaller than One-third the column spacing The column spacing Three-fourth the column spacing Half the column spacing One-third the column spacing The column spacing Three-fourth the column spacing Half the column spacing ANSWER DOWNLOAD EXAMIANS APP
Building Construction The skirting/dado in a bath roof should be upto 15 cm above floor level Level of the tap Ceiling 200 cm 15 cm above floor level Level of the tap Ceiling 200 cm ANSWER DOWNLOAD EXAMIANS APP
Building Construction To obtain good bonding in brick masonry Vertical joints in alternate courses are kept in plumb line All of these Bats are used where necessary First class bricks are used Vertical joints in alternate courses are kept in plumb line All of these Bats are used where necessary First class bricks are used ANSWER DOWNLOAD EXAMIANS APP
Building Construction As compared to stretcher course, the thickness of joints in header course should be Equal Less More Equal or more Equal Less More Equal or more ANSWER DOWNLOAD EXAMIANS APP