Building Construction The stone masonry of finely dressed stones laid in cement or lime, is Ashlar masonry Dry rubble masonry Random rubble masonry Coursed rubble masonry Ashlar masonry Dry rubble masonry Random rubble masonry Coursed rubble masonry ANSWER DOWNLOAD EXAMIANS APP
Building Construction The process of making the back ground rough, before plastering, is Peeling Dubbing Hacking Blistering Peeling Dubbing Hacking Blistering ANSWER DOWNLOAD EXAMIANS APP
Building Construction Suitable spacing of timber piles, is 90 cm 80 cm 100 cm 70 cm 90 cm 80 cm 100 cm 70 cm ANSWER DOWNLOAD EXAMIANS APP
Building Construction Cavity wall is generally provided for Heat insulation All of these Sound insulation Prevention of dampness Heat insulation All of these Sound insulation Prevention of dampness ANSWER DOWNLOAD EXAMIANS APP
Building Construction Arches in the form of masonry arcs struck from more than four centres, are called Drop gothic arches Ogee arches Gothic arches Two curved arches Drop gothic arches Ogee arches Gothic arches Two curved arches ANSWER DOWNLOAD EXAMIANS APP
Building Construction The floor is rubbed with oxalic acid, for making its surface Durable Free from voids Glossy Uniform Durable Free from voids Glossy Uniform ANSWER DOWNLOAD EXAMIANS APP