Industrial Engineering and Production Management The start or completion of task is called None of these An event A duration An activity None of these An event A duration An activity ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management Pessimistic time is The average time required for a job The most probable time considering all conditions The minimum time in which an activity can possibly be accomplished The maximum time which an activity might require The average time required for a job The most probable time considering all conditions The minimum time in which an activity can possibly be accomplished The maximum time which an activity might require ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management Job enrichment technique is applied to Overcome boring and demotivating work Reduce labour monotony Make people happy All of the listed here Overcome boring and demotivating work Reduce labour monotony Make people happy All of the listed here ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management In ABC control policy, maximum attention is given to Those items which consume more money Those × items which are in more demand Those items which are not readily available Those items which consume money Those items which consume more money Those × items which are in more demand Those items which are not readily available Those items which consume money ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management In the Emerson efficiency plan, a worker receives only his daily wage and no bonus is paid till his efficiency reaches 0.75 0.6667 0.5 0.8 0.75 0.6667 0.5 0.8 ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management PERT has following time estimate Two time estimate Three time estimate One time estimate Four time estimate Two time estimate Three time estimate One time estimate Four time estimate ANSWER DOWNLOAD EXAMIANS APP