Industrial Engineering and Production Management The important file in making a PERT is No activity from any event can be started from preceding event till it is completed An event can't be accomplished until activities leading to it are completed All of the these Length of arrow has nothing to do with time No activity from any event can be started from preceding event till it is completed An event can't be accomplished until activities leading to it are completed All of the these Length of arrow has nothing to do with time ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management If E is the duration, ES and EF are die earliest start and finish times, LS and LF are latest start and finish times, then the following relation holds good EF = ES + D All of these LF = LS + D LS = LFD EF = ES + D All of these LF = LS + D LS = LFD ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management Statistical quality control techniques are based on the theory of Statistics All of the these Probability Quality Statistics All of the these Probability Quality ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management The factors which are to be considered while developing a good wage incentive plan will include Adequate incentive Ease of administration Guaranteed basic pay All of the listed here Adequate incentive Ease of administration Guaranteed basic pay All of the listed here ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management The standard time for a job is Total work content + basic time Total work content + delay contingency allowance Base time + relaxation time Total work content Total work content + basic time Total work content + delay contingency allowance Base time + relaxation time Total work content ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management When slack of an activity is positive Any one of the above It represents a situation where extra resources are available and the completion of project is not delayed The activity is critical and any delay in its performance will delay the completion of whole project It represents that a programme falls behind schedule and additional resources are required to complete the project in time Any one of the above It represents a situation where extra resources are available and the completion of project is not delayed The activity is critical and any delay in its performance will delay the completion of whole project It represents that a programme falls behind schedule and additional resources are required to complete the project in time ANSWER DOWNLOAD EXAMIANS APP