Industrial Engineering and Production Management The purpose of micro-motion study is to Help in collecting the motion time data for synthetic time standards Train the individual operator regarding the motion economy principles All of these Assist in finding out the most efficient way of doing work Help in collecting the motion time data for synthetic time standards Train the individual operator regarding the motion economy principles All of these Assist in finding out the most efficient way of doing work ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management Work study is mainly aimed at Establishing the minimum time of completion of a job Determining the most efficient method of performing a job Economizing the motions involved on the part of the worker while performing a job Developing the standard method and standard time of a job Establishing the minimum time of completion of a job Determining the most efficient method of performing a job Economizing the motions involved on the part of the worker while performing a job Developing the standard method and standard time of a job ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management Which of the following are the principles of material handling? All of these Select only efficient handling equipment Move the heaviest weight to the least distance Keep all the handling to the minimum All of these Select only efficient handling equipment Move the heaviest weight to the least distance Keep all the handling to the minimum ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management A dummy activity Does not require any time All of the these Is represented by a dotted line Is artificially introduced Does not require any time All of the these Is represented by a dotted line Is artificially introduced ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management If A is the total items consumed per year, P is the procurement cost per order, and C is the annual inventory carrying cost per item, then the most economic ordering quantity is given by √(2AP/C) 2AP/C (AP/C)² AP/C √(2AP/C) 2AP/C (AP/C)² AP/C ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management Templates are used for Flow of material Copying complicated profiles Advancing a programme in automatic machines A planning layout Flow of material Copying complicated profiles Advancing a programme in automatic machines A planning layout ANSWER DOWNLOAD EXAMIANS APP