MGVCL Exam Paper (30-07-2021 Shift 1)
The operating time of an inverse definite minimum time (IDMT) overcurrent relay corresponding to plug-setting multiplier (PSM) = 1 and time-multiplier setting (TMS) = 1 will be

1 sec
zero
3 sec
infinite

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP

MGVCL Exam Paper (30-07-2021 Shift 1)
A 16 A, Type B Miniature Circuit Breaker (MCB) will disconnect a fault in 0.1s when the fault current is

greater than 32 A
less than 16 A
between 48 A and 80 A
less than 16 A

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP

MGVCL Exam Paper (30-07-2021 Shift 1)
Three equal star-connected inductors take 8 kW at 0.8 power factor when connected to a 460 V three - phase 3-wire supply. If one of the inductor in phase – Y is short circuited, then the line current in phase-Y is ___ Assume RYB sequence.

37.6 A
21.7 A
27.6 A
31.7 A

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP

MGVCL Exam Paper (30-07-2021 Shift 1)
Which among the following are included in the two part tariff?
i. Fixed charges
ii. Running charges
iii. Semi fixed charges

(ii) and (iii) only
(i) and (iii) only
(i) and (ii) only
(i), (ii) and (iii)

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP