Building Construction The number of steps in a flight generally should not be less than No limit 2 5 3 No limit 2 5 3 ANSWER DOWNLOAD EXAMIANS APP
Building Construction In the method of tube boring of soil investigation, the following is essential: A tube of about 2 meters length and 20 cm diameter with a cutting edge All listed here A flap valve at the bottom of tube is provided to extract the soil sample The tube is raised and lowered by 4 thick rope moving over a pulley suspended on a tripod stand A tube of about 2 meters length and 20 cm diameter with a cutting edge All listed here A flap valve at the bottom of tube is provided to extract the soil sample The tube is raised and lowered by 4 thick rope moving over a pulley suspended on a tripod stand ANSWER DOWNLOAD EXAMIANS APP
Building Construction In case of foundations on sandy soil, maximum permissible differential settlement, is usually limited to 45 mm 25 mm 15 mm 35 mm 45 mm 25 mm 15 mm 35 mm ANSWER DOWNLOAD EXAMIANS APP
Building Construction The line of intersection of two surfaces of a sloping roof forming an internal angle less than 180°, is known as Hip Ridge None of these Valley Hip Ridge None of these Valley ANSWER DOWNLOAD EXAMIANS APP
Building Construction While investigating the site, a thick layer of fairly firm clay over a deep layer of soft clay is encountered. In such a situation, the following type of foundation is useful: None of these Raft foundation Grillage foundation Pile formation None of these Raft foundation Grillage foundation Pile formation ANSWER DOWNLOAD EXAMIANS APP
Building Construction The minimum distance between the centers of bulb of diameter du, of a multi under reamed piles, is 1.5 du 1.25 du 1.35 du 1.75 du 1.5 du 1.25 du 1.35 du 1.75 du ANSWER DOWNLOAD EXAMIANS APP